Saturday, June 15, 2013

Hard Labor Creek Management Board Set To Consider $28 Million Budget At Meeting On Tuesday

Big Item: Dam Construction

The Hard Labor Creek Regional Reservoir Management Board is scheduled to consider on Tuesday the $28.2 million fiscal year 2014 project budget, which includes $15 million for construction of the dam and spillway for the reservoir in southeast Walton County.

The budget also includes $2.8 million for construction of the reservoir intake and pump and $3.5 million to relocate Social Circle Fairplay Road.

The spending in fiscal year 2014 will be financed by $5.6 million from the proceeds of bonds already sold by the two counties and by $22.6 million in state loans.

By the end of the fiscal year on June 30, 2014, Walton and Oconee counties are budgeted to have spent $74.1 million of the $170.3 million estimated cost of phase one of the reservoir on Hard Labor Creek.

The two counties still must raise $86.4 million to cover the remaining costs of the project’s first phase, including $34 million needed for construction of the water treatment facility and $21.3 million for the water transmission lines.

Joint Meeting

The Management Board will be meeting on Tuesday with the Walton County Water and Sewerage Authority, which has ultimate budget authority for the project.

The proposed budget was distributed to the Management Board at its meeting on April 16.

Project Manager Jimmy Parker warned the Board he was presenting them with “a lot of numbers.”

Parker said that the intergovernmental agreement between Walton and Oconee counties required passage of a project construction budget each year. That 2007 document specifies that Oconee County pays 28.8 percent of the costs of the project and will receive that same percentage of water.

The Management Board did not gather in May, so the meeting next week will be the first time the Board will have the chance to publicly discuss the budget Parker presented to it. That meeting is to start at 1 p.m. at the Walton County Government Building in Monroe.

Expenses Detailed

The 2014 budget contains $1.8 million for continued land acquisition for the reservoir. Parker reported at the April meeting that the Board had been able to close on 90 percent of the 2,468 acres needed for the project.

The budget includes a little more than $1 million for reconstruction of Mt. Paron Church Road, the second road affected significantly by the project.

It also includes $650,753 for relocation of a power line and $920,971 for stream buffer preservation.

The budget also includes $70,000 in administrative costs, largely for Parker and others at Precision Planning Inc., where Parker is an engineer.

Income Sources

Funding for the 2014 budget comes from three sources.

The two counties have sold bonds for the project, and $5.6 million left over from those bond sales will be used in 2014. Oconee County sold $19.5 million in bonds in 2008 as its part of the project.

The budget calls for spending $19.1 million of the first of two loans the two counties have received from the Georgia Environmental Finance Authority (GEFA) through the Governor's Water Supply Program. The full amount of that loan is $20 million.

Another $3.4 million in GEFA funds–from a second loan of $10.4 million–also will be spent in 2014, according to the budget.

At the end of the 2014 fiscal year, the Board will have $9.8 million in unspent funds from the bonds and the two loans.

Budgets Compared

Parker also provided the Board with an update on the 2013 budget of $34.8 million.

That budget included $12.9 million in dam and spillway construction, but, as of March 31, almost none of that money had been spent.

The next biggest item in the budget–$7.2 million--was for land acquisition, and three-quarters of that amount had been spent by the March 31 date.

The budget included $4.8 million for constructioin of the relocated Social Circle Fairplay Road, and little of that had been spent, and $2.9 million for construction of the reservoir intake and pump. None of the latter had been spent by March 31.

The 2013 fiscal year budget included $70,000 in administrative costs.

Media Coverage Missing

Normally there are no journalists at Hard Labor Creek Management Board meetings, and there were none at the April 16 meeting, when Parker released the budgets.

Usually there are only a few citizens present, and I was the only one at the April 16 meeting.

Road Closures Map

Following the session, Parker provided me, at my request, the same budget information he had given to the Board members. His colleague at PPI, William Crowder, answered questions I posed to him on May 10 about the budgets.

Though the Management Board is chaired by Oconee County Commissioner Jim Luke, Parker generally handles most of the agenda items at Board meetings.

New Board Members

Oconee County Commissioner Mark Saxon attended his first Management Board meeting on April 16, where he was seated as an alternate.

Saxon will be a voting member at the meeting on Tuesday.

That meeting will be the first that Chuck Horton and John Caudill can attend as newly selected, non-voting citizen alternate members to the Board.

Horton had been a member when he had served on the Oconee County Board of Commissioners, and he and Caudill were appointed as alternates by the BOC on May 7

Time Frame

Parker told the Board at the April meeting that he expects land acquisition to be completed this summer, and that work on the dam will begin as soon as possible after that. Work on the intake facility is underway and is to be completed in a little more than a year.

The reservoir is projected to be filled by 2018. No plans have yet been put forward for construction of the water treatment plant or the transmission lines. The project has been delayed because of slow population growth in the two counties.

The Board already has let bids for the Social Circle Fairplay Road and Mount Paron Church Road relocations.

Parker presented the Board with a map notifying the public of the road closures at the April meeting. (Click on the map above to enlarge it.)

The second phase of the project, which would double the cost, involves diverting water from the Apalachee River to the reservoir to increase the amount of water available for treatment. No timetable has been set for that phase of the project.

Friday, June 14, 2013

Oconee County Sees Population Growth Rate of 2.5 Percent From 2010 to 2012

Most Recent Estimate

Oconee County’s population increased by 804 individuals between April 1, 2010, and July 1, 2012, according to the latest estimate by the U.S. Census Bureau.

The growth rate for Oconee County of 2.5 percent is just slightly higher than the growth rate of 2.4 percent for the state as a whole.

In adding 804 residents, Oconee County nearly matched the 807 added in Walton County and just beat the 802 added in Barrow County. Because those two counties have a larger base, their rates of growth were below those of Oconee County.

Clarke County was the real center of growth among the counties surrounding Oconee County. It added 3,552 individuals, representing a growth rate of 3.0 percent, the highest among the seven counties surrounding Oconee.

Population Estimate Program

The data, released yesterday, are from the Census Bureau's Population Estimates Program (PEP) and do not represent real counts. Actual counts occur only every 10 years, with the last in 2010.

(Click on the graphic below to enlarge it.)


The Census Bureau utilizes data on births, deaths and migration to calculate population change from the most recent census.

The projections are just that, and the Census Bureau in 2010 counted fewer residents in the county than its earlier projections indicated would be the case. The population actually grew 25.1 percent during that 10-year time period.

The reference point for the change rates reported by the Census Bureau yesterday is April 1, 2010.

Oconee County had an estimated 32,815 residents on that date. The actual Census Bureau count for Jan. 1, 2010, was 32,808.

Oglethorpe Lost Population

Oglethorpe County lost population between 2010 and 2012, according to the Census Bureau. It was the only county of the seven that Oconee borders that did not add residents.

Greene, Jackson and Morgan counties added fewer than 100 residents.

The growth rates in none of the counties other than Oconee and Clarke were more than 2 percent.

The Census Bureau last year projected growth of just less than 1.7 percent (551 individuals, or 36.7 per month) for Oconee County for the 15 months from April 1, 2010, to July 1, 2011, so the increase of 253 individuals in the next 12 months (21.1 per month) represents a slowdown in growth.

Population Estimates Important

Population estimates are used by government officials to gauge needed services, which often require years to bring online.

The average household in Oconee County, according to Census Bureau data, contains 2.87 individuals, so the 804 individuals added in the April 1, 2010, to July 1, 2012, period represents roughly 280 households.

Oconee and Walton counties have used strong growth rate estimates to justify construction of Hard Labor Creek Regional Reservoir in Walton County. That project was slowed down when the housing market in the two counties collapsed and demand for water was less than projected.

The two counties are moving forward with construction of the dam and reservoir intake and pump, but they have not made any decision about when to build the water treatment plant and the water transmission system.

Estimates of population growth for each of the state’s counties are available from the QuickFacts feature of the Census Bureau web site.

Monday, June 10, 2013

Called Meeting of Oconee County Commissioners To Deal With Sewer Capacity Fees

Changes For Pending Projects

The Oconee County Board of Commissioners is scheduled to meet at 5:15 p.m. tomorrow evening in a called meeting to consider changes to the county’s policy on computation of sewer capacity fees.

Utility Department Director Chris Thomas told me on Friday that he is proposing that the county change when capacity fees are paid and how they are calculated.

Sunday, June 09, 2013

Oconee County Code Enforcement Office Logged Complaints In April And May Against Oconee Waste Transport

Loud Banging Noise Cited

Oconee County Code Enforcement has logged five complaints against Oconee Waste Transport following acknowledgment by the county in early April that it had agreed to allow the company to operate in violate of a county zoning ordinance in part because neighbors had stopped complaining.

Five different residents of the small subdivision off Greene Ferry Road south of Watkinsville complained to the county on three different dates in late April and early May that OWT was operating before 6 a.m.

Monday, June 03, 2013

Oconee County Commissioners Set To Adopt FY 2014 Budget With Water And Sewer Rate Increases

Sheriff Gets Deputies

The Oconee County Board of Commissioners tomorrow night is expected to adopt a fiscal year 2014 General Fund budget that is up 5.7 percent from a year earlier but $2.7 million less than department heads and constitutional officers had requested.

The overall county budget includes water and sewer rate increases, with residential water customers paying $19 for the first 1,000 gallons of water used, up 5.6 percent from the current $18, and residential sewer customers paying $21.32, up 4.0 percent from a year earlier.

Sunday, June 02, 2013

County Attorney’s Change Of View Precedes Oconee County Commissioners’ Vote To Approve Beer And Wine License For Theater

No Monitoring Acknowledged

The Oconee County Board of Commissioners last week voted to approve the beer and wine license for University 16 Cinema after the theater owner scaled back from three to one the number of auditoriums in which food and alcohol would be sold.

That change led County Attorney Daniel Haygood to drop his opposition to the request and conclude that a restaurant that includes a theater does not necessarily violate the county’s definition of a restaurant as spelled out in the beer and wine ordinance.

Sunday, May 26, 2013

Georgia Theatre Company Asking Oconee County Commissioners To Expand Definition Of Restaurant

Developer Bishop Involved

If the Oconee County Board of Commissioners grants a beer and wine license for the University 16 Cinemas on Tuesday night, it will be expanding the meaning of restaurant from what currently is listed in the alcoholic beverages ordinance passed by the county in 2008.

The Board also will be going against, at least to some extent, the recommendation of County Attorney Daniel Haygood.